This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

SSE Thermal Generation and Gas Storage REMIT information is no longer being updated on this page.
For SSE Thermal Generation and Gas Storage REMIT Information (Unavailability of Facilities and Other Market Information), please visit SSE Thermal REMIT.

Last update at: 2026-10-06T16:00:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
1 2 3 4 5 >
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000011206_005 Active Unplanned Consumption unavailability 2026-10-06T15:59:37+01:00 2026-10-05T15:15:15+01:00 2026-10-06T22:00:00+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000011206_004 Dismissed Unplanned Consumption unavailability 2026-10-06T15:58:12+01:00 2026-10-05T15:15:15+01:00 2026-10-06T22:00:00+01:00 MW 150 0 150 Failure
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000011206_003 Dismissed Unplanned Consumption unavailability 2026-10-05T15:46:28+01:00 2026-10-05T15:15:15+01:00 2026-10-06T18:00:00+01:00 MW 150 0 150 Failure
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000011206_002 Dismissed Unplanned Consumption unavailability 2026-10-05T15:06:28+01:00 2026-10-05T15:15:15+01:00 2026-10-05T22:00:00+01:00 MW 150 0 150 Failure
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000011206_001 Dismissed Unplanned Consumption unavailability 2026-10-05T14:32:41+01:00 2026-10-05T15:15:15+01:00 2026-10-05T18:00:00+01:00 MW 150 0 150 Failure
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011209_002 Active Planned Consumption unavailability 2026-10-06T15:58:57+01:00 2026-10-06T09:10:34+01:00 2026-10-06T22:00:47+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011209_001 Dismissed Planned Consumption unavailability 2026-10-06T08:11:50+01:00 2026-10-06T09:10:34+01:00 2026-10-06T18:00:47+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000011208_002 Active Unplanned Production unavailability 2026-10-06T15:57:18+01:00 2026-10-05T16:47:32+01:00 2026-10-06T17:00:36+01:00 MW 150 0 150 Failure
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000011208_001 Dismissed Unplanned Production unavailability 2026-10-05T15:48:17+01:00 2026-10-05T16:47:32+01:00 2026-10-06T18:00:36+01:00 MW 150 0 150 Failure
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000011207_002 Active Unplanned Production unavailability 2026-10-05T15:05:08+01:00 2026-10-05T15:34:11+01:00 2026-10-05T16:15:00+01:00 MW 150 0 150 Failure
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000011207_001 Dismissed Unplanned Production unavailability 2026-10-05T14:35:57+01:00 2026-10-05T15:34:11+01:00 2026-10-05T18:00:35+01:00 MW 150 0 150 Failure
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011205_002 Active Planned Consumption unavailability 2026-10-05T09:54:16+01:00 2026-10-04T18:00:00+01:00 2026-10-05T22:00:00+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011205_001 Dismissed Planned Consumption unavailability 2026-10-04T16:32:58+01:00 2026-10-04T18:00:00+01:00 2026-10-05T12:00:00+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000011204_001 Active Planned Consumption unavailability 2026-10-02T21:45:02+01:00 2026-10-02T22:45:44+01:00 2026-10-03T12:00:55+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011191_007 Active Planned Consumption unavailability 2026-10-02T16:16:48+01:00 2026-09-29T15:30:53+01:00 2026-10-02T17:30:00+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011191_006 Dismissed Planned Consumption unavailability 2026-10-01T13:20:57+01:00 2026-09-29T15:30:53+01:00 2026-10-02T20:00:00+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011191_005 Dismissed Planned Consumption unavailability 2026-09-30T12:53:40+01:00 2026-09-29T15:30:53+01:00 2026-10-02T13:00:00+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011191_004 Dismissed Planned Consumption unavailability 2026-09-30T12:13:50+01:00 2026-09-29T15:30:53+01:00 2026-10-01T13:00:00+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011191_003 Dismissed Planned Consumption unavailability 2026-09-30T07:34:40+01:00 2026-09-29T15:30:53+01:00 2026-10-01T23:59:44+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011191_002 Dismissed Planned Consumption unavailability 2026-09-29T14:55:42+01:00 2026-09-29T15:30:53+01:00 2026-09-30T23:59:44+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011191_001 Dismissed Planned Consumption unavailability 2026-09-29T13:23:36+01:00 2026-09-29T15:30:53+01:00 2026-09-29T23:00:44+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011192_005 Active Planned Production unavailability 2026-10-02T16:16:06+01:00 2026-09-29T15:58:15+01:00 2026-10-02T17:30:00+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011192_004 Dismissed Planned Production unavailability 2026-10-01T13:21:20+01:00 2026-09-29T15:58:15+01:00 2026-10-02T20:00:00+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011192_003 Dismissed Planned Production unavailability 2026-09-30T12:13:12+01:00 2026-09-29T15:58:15+01:00 2026-10-02T13:00:00+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011192_002 Dismissed Planned Production unavailability 2026-09-30T07:35:07+01:00 2026-09-29T15:58:15+01:00 2026-10-01T23:59:38+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000011192_001 Dismissed Planned Production unavailability 2026-09-29T14:55:12+01:00 2026-09-29T15:58:15+01:00 2026-09-30T23:59:38+01:00 MW 150 0 150 Shutdown
Water Management
Hydro Pumped Storage 10YGB----------A
T_CLDNW-1 48W00000CLDNW-1Q
Clyde Windfarm (Scotland) Limited
48X000000000071Y 0000000000000000000011203_003 Active Unplanned Production unavailability 2026-10-02T12:35:36+01:00 2026-10-02T12:20:42+01:00 2026-10-02T13:40:48+01:00 MW 101 86 187 Shutdown
Maintenance
Wind Onshore 10YGB----------A
T_CLDNW-1 48W00000CLDNW-1Q
Clyde Windfarm (Scotland) Limited
48X000000000071Y 0000000000000000000011203_002 Dismissed Unplanned Production unavailability 2026-10-02T12:14:52+01:00 2026-10-02T12:20:42+01:00 2026-10-02T13:50:48+01:00 MW 101 86 187 Shutdown
Maintenance
Wind Onshore 10YGB----------A
T_CLDNW-1 48W00000CLDNW-1Q
Clyde Windfarm (Scotland) Limited
48X000000000071Y 0000000000000000000011203_001 Dismissed Unplanned Production unavailability 2026-10-02T11:24:53+01:00 2026-10-02T12:20:42+01:00 2026-10-02T13:20:48+01:00 MW 101 86 187 Shutdown
Maintenance
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011174_004 Dismissed Planned Production unavailability 2026-10-02T07:46:39+01:00 2026-09-19T14:50:57+01:00 2026-09-19T17:00:06+01:00 MW 102 0 102 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011174_003 Dismissed Planned Production unavailability 2026-09-19T14:53:57+01:00 2026-09-19T14:50:57+01:00 2026-09-19T17:00:06+01:00 MW 102 0 102 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011174_002 Dismissed Planned Production unavailability 2026-09-19T13:47:38+01:00 2026-09-19T14:50:57+01:00 2026-09-19T16:00:06+01:00 MW 102 0 102 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011174_001 Dismissed Planned Production unavailability 2026-09-19T10:35:57+01:00 2026-09-19T14:00:57+01:00 2026-09-19T16:00:06+01:00 MW 102 0 102 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_GRIFW-2 48W00000GRIFW-2Y
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011175_003 Dismissed Planned Production unavailability 2026-10-02T07:46:15+01:00 2026-09-19T14:50:22+01:00 2026-09-19T16:00:31+01:00 MW 102 0 102 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_GRIFW-2 48W00000GRIFW-2Y
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011175_002 Dismissed Planned Production unavailability 2026-09-19T13:47:13+01:00 2026-09-19T14:50:22+01:00 2026-09-19T16:00:31+01:00 MW 102 0 102 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_GRIFW-2 48W00000GRIFW-2Y
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011175_001 Dismissed Planned Production unavailability 2026-09-19T10:36:58+01:00 2026-09-19T14:00:22+01:00 2026-09-19T16:00:31+01:00 MW 102 0 102 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_GRIFW-2 48W00000GRIFW-2Y
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011165_005 Dismissed Planned Production unavailability 2026-10-02T07:46:01+01:00 2026-09-19T10:00:00+01:00 2026-09-19T11:40:00+01:00 MW 102 0 102 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_GRIFW-2 48W00000GRIFW-2Y
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011165_004 Dismissed Planned Production unavailability 2026-09-19T10:33:56+01:00 2026-09-19T10:00:00+01:00 2026-09-19T11:40:00+01:00 MW 102 0 102 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_GRIFW-2 48W00000GRIFW-2Y
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011165_003 Dismissed Planned Production unavailability 2026-09-19T09:11:09+01:00 2026-09-19T10:00:00+01:00 2026-09-19T12:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_GRIFW-2 48W00000GRIFW-2Y
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011165_002 Dismissed Planned Production unavailability 2026-09-19T09:10:12+01:00 2026-09-19T10:10:00+01:00 2026-09-19T12:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_GRIFW-2 48W00000GRIFW-2Y
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011165_001 Dismissed Planned Production unavailability 2026-09-09T10:56:59+01:00 2026-09-19T16:00:00+01:00 2026-09-19T17:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011164_003 Dismissed Planned Production unavailability 2026-10-02T07:45:48+01:00 2026-09-19T10:00:00+01:00 2026-09-19T12:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011164_002 Dismissed Planned Production unavailability 2026-09-19T09:10:47+01:00 2026-09-19T10:00:00+01:00 2026-09-19T12:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
Griffin Wind Farm Limited
48X000000000072W 0000000000000000000011164_001 Dismissed Planned Production unavailability 2026-09-09T10:55:28+01:00 2026-09-19T16:00:00+01:00 2026-09-19T17:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_GORDW-1 48W00000GORDW-1D
SSE GENERATION
48X000000000077M 0000000000000000000011168_006 Dismissed Unplanned Production unavailability 2026-10-02T07:45:28+01:00 2026-09-15T18:20:15+01:00 2026-09-16T13:30:24+01:00 MW 70 0 70 Failure
Plant Fault - Auxiliary Equipment
Wind Onshore 10YGB----------A
T_GORDW-1 48W00000GORDW-1D
SSE GENERATION
48X000000000077M 0000000000000000000011168_005 Dismissed Unplanned Production unavailability 2026-09-16T11:15:00+01:00 2026-09-15T18:20:15+01:00 2026-09-16T13:30:24+01:00 MW 70 0 70 Failure
Plant Fault - Auxiliary Equipment
Wind Onshore 10YGB----------A
T_GORDW-1 48W00000GORDW-1D
SSE GENERATION
48X000000000077M 0000000000000000000011168_004 Dismissed Unplanned Production unavailability 2026-09-15T19:53:04+01:00 2026-09-15T18:20:15+01:00 2026-09-16T17:00:24+01:00 MW 70 0 70 Failure
Plant Fault - Auxiliary Equipment
Wind Onshore 10YGB----------A
T_GORDW-1 48W00000GORDW-1D
SSE GENERATION
48X000000000077M 0000000000000000000011168_003 Dismissed Unplanned Production unavailability 2026-09-15T19:25:13+01:00 2026-09-15T18:20:15+01:00 2026-09-15T21:30:24+01:00 MW 70 0 70 Failure
Plant Fault - Auxiliary Equipment
Wind Onshore 10YGB----------A
T_GORDW-1 48W00000GORDW-1D
SSE GENERATION
48X000000000077M 0000000000000000000011168_002 Dismissed Unplanned Production unavailability 2026-09-15T18:05:54+01:00 2026-09-15T18:20:15+01:00 2026-09-15T20:30:24+01:00 MW 70 0 70 Failure
Plant Fault - Auxiliary Equipment
Wind Onshore 10YGB----------A
T_GORDW-1 48W00000GORDW-1D
SSE GENERATION
48X000000000077M 0000000000000000000011168_001 Dismissed Unplanned Production unavailability 2026-09-15T17:20:51+01:00 2026-09-15T18:20:15+01:00 2026-09-15T19:20:24+01:00 MW 70 0 70 Failure
Plant Fault - Auxiliary Equipment
Wind Onshore 10YGB----------A